Floor construction process
 May 20, 2011|View:284

Floor construction process
1 To install the elevated ground floor of the venue clean, dry and flat surface required. Cement mortar should be ready leveling the ground, high and low levels of bad feet with a 2 m measuring less than 4 mm
2 shells land in a clean line of good positioning, the purpose of determining a good location for each bracket.
3 position in the fixed mounting bracket, install the border and adjust the height of the bracket.
4 support beam assembly, while adjusting beam levels, laser level is recommended, and then tighten the screw and fixed beams.
5 Install the raised floor, raised floor while trimming.
6, the baseboard on the floor after the installation to install, protect and beautify the wall.
7, after construction of the floor surface.
 